Treatment Mounds
Table of Contents
| Standard of Practice | Explanation |
8. Treatment Mounds |
See Pg. 197, Fig. Typical M 1 in Appendix "B" |
8.1 Design Standard |
|
8.1.1. Notwithstanding Article 7.1.5. , a treatment mound may be constructed on soils where
|
The treatment mound is most often used on difficult soils where a disposal field will not work well. A key requirement to building a successful mound is the use of high quality, clean sand in the sand layer and the proper soil for the berms and cover of the mound. See Pg. 38, Article 7.1.6. for Vertical Separation Requirements. |
8.1.2. The sand layer receiving effluent shall
Intent: Clause 8.1.2.(e) requires the mound to be built on the existing grade of the soil. Soil should not be stripped away creating a depression in the ground or be stripped away and replaced by fill material. |
Making the sand layer narrower than 10 feet and longer can provide a better working and more effective mound. See Pg. 198, Fig. M1 in Appendix "B" |
8.1.3. The area of the mound within the berm, excluding the end slopes, providing the infiltration area into the original soil shall
Intent: The intent of this Article is to assure that an adequate area of soil is available for the effluent to infiltrate, that this area is fully covered by the berm, and that the permeability of the berm fill material is suitable to distribute the effluent over the infiltration area. |
The infiltration area required under the treatment mound is 70 % of the area required for a disposal field because of the additional treatment of the effluent provided in the sand layer prior to the effluent entering the soil. See Pg. 198, Fig. M1 in Appendix "B" |
8.1.4. The distribution of effluent into the sand layer shall be into
|
See Pg. 198, Fig. M1 in Appendix "B" |
8.1.5. Where chambers are used
|
See Pg. 202, Fig. M3 in Appendix "B" |
| 8.1.6. The designed quantity of effluent delivered to the mound per pump cycle, shall not exceed 25% of the estimated or measured daily sewage flow.
Intent: Smaller doses provide better treatment conditions. Doses may be smaller than 25%. |
Note: Gravity distribution of effluent in a treatment mound is not permitted. A treatment mound is a closed system that is sensitive to internal hydraulic pressures which can cause a breakout at the sides of the mound if hydraulically overloaded. See Pg. 182, Fig. DF 1B in Appendix "B" |
| 8.1.7. Distribution of effluent shall be by distribution laterals under pressure. |
Note: Gravity distribution of effluent in a treatment mound is not permitted. |
| 8.1.8. The effluent pump rate of discharge shall be sufficient to distribute effluent effectively throughout the distribution laterals while maintaining pressure head in accordance with Table A.1.B. .1.B. |
The minimum head pressure as specified in Pg. 73, Table A.1.B. in Appendix "A" is at the farthest point of the distribution laterals from the manifold. Remember to consider pressure loss in effluent line to the treatment mound. See Pg. 75, Table A.1.C.1 in Appendix "A" for friction loss in the effluent line between the septic tank and the treatment mound. |
| 8.1.9. The rate of discharge per orifice diameter and pressure head shall be calculated in accordance with Table A.1.B. | The discharge volume per orifice will change with the head pressure as specified in Pg. 73, Table A.1.B. in Appendix "A" |
| 8.1.10. The maximum number of orifices in distribution laterals shall be in accordance with Table A.1.A. | See Pg. 69, Table A.1.A.. for the number of orifices in given lengths of various diameters of pipe. |
| 8.1.11. Pipe orifices shall be sized to provide relatively even distribution of effluent over the sand layer. |
See Pg. 194, Fig. PDL 3 Squirt Test in Appendix "B" See Pg. 138, Pressure Distribution Lateral Design in Appendix "B" |
8.1.12. Pipe orifices shall be located in the distribution laterals
Intent: Orifices may be placed at the bottom of the piping to help drain the pipe and protect from freezing. Locating the orifice on the upper half of the pipe can help prevent clogging of the orifice. Wherever the orifices are located, there must be room for the water to escape and the spraying water must not cause any erosion of the soil or sand around it. |
When the distribution laterals are installed in gravel, pointing the orifices down will not erode the sand layer. However, there is a greater possibility of orifice clogging and slightly uneven distribution of effluent. If the orifices are pointed up, orifice shields must be provided to prevent gravel from laying on the orifice and restricting the flow or erosion of the soil above. Also, greater care must be taken to ensure the distribution lateral is graded to allow drainage. A few orifices can be drilled to point down to allow for drainage of the pipe. If the distribution laterals are installed inside a chamber, the orifices must be pointed up to prevent erosion of the surface of the sand layer under the chamber. See Pg. 201, Fig. M2 in Appendix "B" |
8.2. Installation Standards |
|
8.2.1. A treatment mound shall not be located within
|
See Pg. 38, Article 7.1.6. for Vertical Separation Requirements. |
| 8.2.2. Whenever mounds are located on slopes, a diversion shall be constructed immediately up slope from the base of the mound to intercept and direct run-off water away from the mound. | See Pg. 21, Article 3.1.6. |
| 8.2.3. The sand layer the effluent is distributed over shall be a minimum of 300 mm (1 ft.) thick and the top of the sand layer shall be nominally level. |
See Pg. 198, Fig. M1 in Appendix "B" |
| 8.2.4. Track type machinery shall be used to move the sand into place and at least 150 mm (6 in.) of sand shall be kept beneath the machinery to minimize compaction of the soil under the sand layer to prevent smearing or glazing of the soil under the mound area. | See Pg. 147, Treatment Mound Design in Appendix "B" |
8.2.5. When gravel is used over the sand layer
|
See Pg. 198, Fig. M1 in Appendix "B" |
8.2.6. The distribution laterals shall be
|
Treatment mounds may be constructed with the contact area between the gravel or chambers and the sand layer less than 3 m (10 feet) wide. When a longer, narrower treatment mound is desired, the number of distribution laterals can be reduced from 3 to 2. A treatment mound with only 2 distribution laterals would have a maximum width of the contact area between the gravel, or chambers, and the sand layer of 2 m (6.5 feet). See Pg. 198, Fig. M1 in Appendix "B" |
| 8.2.7. The manifold pipe shall be connected to the pump discharge pipe and shall slope back toward the pump. |
See Pg. 138, Pressure Distribution Lateral Design in Appendix "B" |
| 8.2.8. Sandy loam fill material shall be placed over the gravel layer or chambers to a depth of 300 mm (1 ft.) in the centre of the mound and to a depth of 150 mm (6 in.) at the sides.
Intent: To provide an adequate slope on the top of the treatment mound to prevent storm water from standing on the top of the mound. |
See Pg. 147, Treatment Mound Design in Appendix "B" |
| 8.2.9. A minimum of 75 mm (3 in.) of top soil shall be placed on the fill material over the entire area of the mound. |
See Pg. 198, Fig. M1 in Appendix "B" |
| 8.2.10. A grass cover shall be established over the entire area of the mound.
Intent: A contractor meets the requirement of this Article by seeding the mound to grass, leaving the responsibility to water and maintain the grass cover to the owner. The grass cover is needed to prevent erosion of the mound and to assist in evaporating the effluent. |
See Pg. 198, Fig. M1 in Appendix "B" |
| 8.2.11. Shrubs shall not be planted on the top of the mound. | |
| 8.2.12. The side slopes on the mound shall not be steeper than 1:4 (one vertical to four horizontal). |
See Pg. 198, Fig. M1 in Appendix "B" |
8.3 Requirements for Materials |
|
8.3.1. Piping materials used in the construction of distribution laterals for a treatment mound shall
|
See Pg. 201, Fig. M2 in Appendix "B" |
| 8.3.2. Sand used for the sand layer shall be a soil texture composed by weight of at least 85% soil particles varying in size from 2.0 mm to 0.05 mm, and containing not more than 10% fines. |
See Pg. 147, Treatment Mound Design in Appendix "B" |
| 8.3.3. Gravel used in the treatment mound shall be 12 mm (½ in.) to 40 mm (1½ in.) particle size containing not more than 5% fines, silt or clay. |



